I have copied the structure and cost from part A into product B in an Estimate.

There is only one operation with a Mach Run Factor of 1.0 hours/unit and an operation cost of 130.00.

I edit the Mach Run Factor to 1.5.

The operation cost remains at 130.00.

Q: Shouldn’t this cost automatically update to 195.00? I believe it did in Apps10.

When I calculate the estimate item the operation cost remains at 130.00.

Q: Shouldn’t the calculation update the operation cost to 195.00?

With the operation cost not updating the Estimate cost is not correct.

Be the first to reply!

Reply