Skip to main content

In our production process we would like to have a different routing after each 50 units which are produced. This alternate routing should send the produced items to an external control center (outside operations) is there a way to implement the requested process in standard IFS. The lot size will not be higher than 10 pcs at the time. So, the alternate routing should be triggered based on the cumulative units produced.

if the part is serial part , you could set it as serial effective, 

then the Routing /structure alternate will be picked based on the serial range that for the SO is created.

 


KanchanaH, thank you for your reply. Currently we are not working with serial items. Is any other way you don’t have to use serial items?