Hi,
There are two questions I’m looking for an answer.
What is the standard procedure of version controlling IFS BR Reports? We have 75+ BR Reports and is there any way of version controlling these in IFS Cloud with Git?
What is the best way of moving reports between environments (Dev → SIT → UAT → PROD) in IFS Cloud with a delivery. I found below topic on this.
Moving Business Reporter Reports between DBs | IFS Community
Is it still the same? We have 75+ BR Reports and it is not practical manually moving between environments. It is also not possible to use Application Configuration Packages with BR Reports.
Is there any workaround we can attach BR Reports with the delivery process in IFS Cloud?
Thanks in advance.
Regards,
Dasun