Hi,

I have created BR report with 2 parameter 

  1. Project
  2. Activity

I used 3 data sources and used ‘custom dimension connection and custom dimension LOV’ windows for connect activity dimension to the project employee allocation source and get LOV for activity. But when running report showing all activities in database instead of selected project. 

 

Appreciate your feedback regarding this issue.

Thanks,

Deepal.

 

 


This topic has been closed for comments

5 replies

Userlevel 5
Badge +13

Hi @TopDeepaW,

 

Please check whether the project code is added as the parent item in the dim_activity.

Example:
 

Best Regards,
Bhagya

Userlevel 2
Badge +6

Hi @Bhagya Wickramasinghe 

 

Yes, This parent item already have.

 

 

Userlevel 5
Badge +13

Hi @TopDeepaW,

When you run the report from the IFS BR application side is the same observed?

Best Regards,
Bhagya

Userlevel 2
Badge +6

Hi @Bhagya Wickramasinghe ,

 

In the BR client it works fine.

 

Regards,

Deepal

 

 

Userlevel 4
Badge +9

Hi @TopDeepaW,

 

Hope you have followed the below documentation. If not please refer these documentations to have a better understanding of the custom dimension LOV.

 

Overview

 

https://docs.ifs.com/techdocs/foundation1/040_administration/255_br_and_a/010_Information_Sources/055_custom_objects/030_Custom_Dim_Lov/005_cust_dim_lov_ovw.htm

 

Examples

 

https://docs.ifs.com/techdocs/foundation1/040_administration/255_br_and_a/010_Information_Sources/055_custom_objects/030_Custom_Dim_Lov/020_Lov_examples.htm

 

Best Regards,

Thiwanka