How to End Production/Approve on open labor and machine time After Monthend?

  • December 1, 2025
  • 0 replies
  • 9 views

Forum|alt.badge.img+2
  • Do Gooder (Customer)

We had employees in production and proceeded to monthend processing.  Typically we check Ongoing clockings, but this was missed this time.  We can end the production as soon as possible on the new month Dec 1st 12:00 AM.  But our hours would still be off.    Our finance dept will not allow reopening, etc. of previous month.  What is the best way to handle this?  thank you!