I was taught to generate POs in IFS Cloud by looking up the WO# in Prepare Work Order, then click view and choose “new maintenance purchase requisition” and create new line for material needed, release and then have to back to prepare work order module and repeat process. sometimes I get requests for more than 10 POs for one work order and I was wondering if there is a way to create them without having to go back to Prepare Work Order module every time I want to create new PO. POs are not always to the same suppliers but are for the same work order.