Hi,
Project transactions are never Authorized, they are Approved…. And if you change this approval is automatically removed.
I the employee’s time report is in status Authorized this only applies on the Time & Attendance result - not the project reporting.
If the employee has a clocking based time reporting it is also possible to change project transactions after authorization.
However there is a property to set in Company details if you want to prevent that. ( New from IFS 9 I think..?)
If the employee has job hour based time reporting it is not possible to change project transactions after authorization of the attendance - since then the change of project hours might change the actual attendance result.
hope this clarifies a bit :-)
//Maria