Question

How to set up a "4 weeks on and 4 weeks off" calendar?

  • 30 December 2022
  • 2 replies
  • 105 views

Userlevel 2
Badge +4

I have created a Schedule for a Period length = 56 days with the following pattern:

4 weeks (28 days)  with Day Type: 24 hours work in 2 shifts
and 
4 weeks with Day Type:  Non-working days (0 hour).

When I generate a calendar, it is just containing the working hours.

Non-working hours are not generated for the 5th to 8th weeks.

Pictures are attached.


2 replies

Userlevel 1
Badge +3

Your pictures can not be loaded, could you please re-attach them?

Userlevel 2
Badge +4

Sure, done :)

Reply