Skip to main content
Question

Is it Possible to Connect an Existing Project Into the Plan of Another Project

  • August 2, 2024
  • 5 replies
  • 101 views

Forum|alt.badge.img+1

Hi all, 

I wanted to know whether it is possible to include an existing project into the plan of another project and be able to add dependencies to it? 

5 replies

Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • August 2, 2024

@rcpowney You can create a project based on an existing project.

When creating the new project enable Copy From Exiting Project and give the existing project as the Source Project.

After the project has been created you can use the same option as well

Alternatively you can copy specific Sub Projects/ Actives as well. Check the Sub Project Scope and Schedule page and/ or Activity Scope and Schedule.


Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 1 reply
  • August 2, 2024
Buddhika Kurera wrote:

@rcpowney You can create a project based on an existing project.

When creating the new project enable Copy From Exiting Project and give the existing project as the Source Project.

After the project has been created you can use the same option as well

Alternatively you can copy specific Sub Projects/ Actives as well. Check the Sub Project Scope and Schedule page and/ or Activity Scope and Schedule.

Hi Buddhika,

Thank you for the reply, I don’t think I have explained myself correctly or are using the correct key words. An example of what I want to know is:

 

I have two existing projects:

  1. Overall project - tracking every phase of the project
  1. A test project - The test project is needed as part of the overall project however, is created mid way through the overall project. 

Both projects ideally need to be kept separate, but I would like to link in the 2nd project into one of the phases of the 1st project. This would let the system schedule the dates instead of having to manually insert dates from one project to the other. 

 

If this is not possible, there is no issue! Was just looking for an easy fix! 

 

Thank you again.


Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • August 2, 2024

@rcpowney I think now it is more clearer :)

If I understand you correct, you need to calculate the dates of some activities of the project #1 based on dates of some activities of a phase of Project #2, taking those as dependencies. But you dont want to copy the mentioned phase of Project #2 to #1. 

If this is the case, I dont see any viable automated functionality in IFS Cloud. 

But if you can identify some constraint dates, you can add those to the activities of the project #1 and do the scheduling.

For example, if an activity cannot be started (in Project #1) before an activity is completed in Project #2, then you can use the end date of the activity of project #2 as a constraint for the activity in project #1 and do the automatic scheduling so that the system will calculate the start end dates for other activities. Not sure if this exactly help in your scenario, but thinking loud.

 


Oshadhi
Sidekick (Employee)
Forum|alt.badge.img+4
  • Sidekick (Employee)
  • 12 replies
  • August 2, 2024

Hi @rcpowney, Currently where are you having your existing projects? Is it already created inside IFS Cloud or created in another external application such as Microsoft Project?

 

Also, would you be able to share a screenshot of your ‘Overall project’ and ‘test project’ to understand better how you have set up your main project, sub projects and activities.

 

A screenshot of the ‘tree navigator’ from both types of projects would suffice to understand better.

(Steps:

  1. Go to Project Scope and Schedule page,
  1. Filter and click on related project’s record
  2. Click Expand all button and take screenshot showcasing the breakdown)

 

Would be interested to know how/to which part you would like to connect your “test project” to the “main project”? Would you like it to be connected as a Sub project or connect if directly to the main project?


Manoja
Do Gooder (Employee)
Forum|alt.badge.img+1
  • Do Gooder (Employee)
  • 3 replies
  • August 5, 2024

Hi @rcpowney , According to your comments, your requirement is to keep one overall project as a program and then more projects underneath that can be operated as own projects. Am I right here? Unfortunately, we dont have that capability in IFS Cloud at the moment. However, if you are only looking to schedule activities in the second project based on phases or milestone dates in the first project, then you can create dependencies between the activities of the two projects. You can do that in the Activity scope and Schedule/Dependencies page then if you schedule both projects by selecting  the Multiple Projects option they will be scheduled as one network.

 


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings