Skip to main content
Solved

IFS Cloud 24R2 to 26R1 Upgrade Process – Questions About Lifecycle, Database Migration, and Testing

  • July 14, 2026
  • 3 replies
  • 91 views

ZTC ZTC JGOTA
Hero (Customer)
Forum|alt.badge.img+14

Hello IFS Community,

I have a few questions regarding the upgrade process from IFS Cloud 24R2 to IFS Cloud 26R1/26R2.

I have previous upgrade experience with IFS Applications 9 to 10 and IFS Cloud 24, but I haven't yet been involved in an upgrade from IFS Cloud 24 to IFS Cloud 26.

I would appreciate any insights on the following:

  1. Database Migration

    • Does IFS take a snapshot of the existing database, perform the upgrade to IFS Cloud 26 in a separate environment, and then provide us with a new URL pointing to the upgraded environment?

    • Or is the upgrade process handled differently?

  2. Lifecycle Environment

    • During the upgrade, does IFS provision a new Lifecycle environment separate from our existing IFS Cloud 24 Lifecycle, or is the existing Lifecycle updated as part of the process?

  3. Testing Timeline

    • At what point in the upgrade project is the upgraded IFS Cloud 26 environment typically made available for customer testing with our data?

    • Approximately how long does it usually take from the start of the upgrade until the test environment is ready?

I'd appreciate hearing about your experiences or any best practices you've learned during a Cloud 24 to Cloud 26 upgrade. Any documentation that you can provide for me to read.

Thank you!

Best answer by ashen_malaka_ranasinghe

Hi ​@ZTC ZTC JGOTA,

The upgrade process from 24R2 to 26R1/26R2 is generally different from the traditional Apps 9 → Apps 10 style upgrades that many of us are familiar with.

For IFS Managed Cloud customers, the upgrade is normally performed in a separate non-production environment first, using a copy of the customer's data. The upgrade activities, technical validation, and customer testing are carried out on that upgraded environment before any production cutover is considered. Therefore, it is not typically a case of directly upgrading the live production environment. The production environment remains on the current release until the customer has completed testing and approved the move to the target version. This aligns with how IFS Cloud Lifecycle and Release Update processes maintain separate tracks for assessment, testing, and deployment.

Regarding the Lifecycle environment, IFS Cloud uses the Application Lifecycle Experience (ALE) and Release Update mechanisms. In practice, the upgrade work is usually performed through a separate release-update branch and upgraded environment rather than by immediately replacing the existing Lifecycle setup. The current customer environment continues to operate on the existing release while impact assessments, release update activities, and testing are performed on the upgraded version. Only after successful validation and customer acceptance is the upgraded solution promoted toward production.

For more information refer to: 26R1 - Impact Assessment and Release Update Assessment | IFS Community

For the testing timeline, the upgraded environment is typically made available after the initial technical upgrade and validation activities have been completed. This environment is then used for functional testing, regression testing, integration testing, reporting validation, and verification of customizations and configurations. The exact timing varies considerably depending on factors such as database size, number of integrations, level of customization, reporting landscape, data volume, and any remediation work required due to functional or technical changes between releases. Because of these variables, there is no universally applicable duration from project start to test-environment availability. The best source for an estimate is usually the IFS Upgrade Project Team or Cloud Operations team assigned to the specific engagement.

One best practice I would strongly recommend is to start reviewing the 26R1/26R2 Release Notes, Technical Documentation, Upgrade Considerations, and Deprecation Information as early as possible. Pay particular attention to customizations, integrations, reporting solutions, permission sets, and any technology changes introduced in 25R2 and later releases, especially areas related to Near-Zero Downtime (NZD), EBR compliance, and other platform-level enhancements that may require uplift activities before the final upgrade.

3 replies

InfFilipV
Hero (Partner)
Forum|alt.badge.img+13
  • Hero (Partner)
  • July 15, 2026

Hello,

Based on my experience, the Release Update process works as follows:

  1. The Release Update is applied to the existing environment through a delivery.

  2. The Release Update process works with a clone of the state from the selected, usually latest, delivery. However, the environments in Release Update Studio do not contain data transferred through TDM. This data is promoted only as the final step of the Release Update process.

Therefore, the work in the Build Place is performed in a clean environment, and the delivery is created based on the state of the latest sanity build.

  1. Only after the delivery has been created successfully can it be installed in a Use Place environment and tested with actual customer data.

The Release Update process requires a considerable amount of machine processing time. You should expect it to take approximately one week, although planning for two weeks is safer.

 

Release Update Studio - LE Documentation For IFS Cloud

BR


Forum|alt.badge.img+2
  • Do Gooder (Partner)
  • July 15, 2026

Hi

 

Please also be aware that if you have any customizations they may need to be altered during the upgrade to work with Oracle EBR that is part of IFS in version 26 that you plan to upgrade to.

 

Tools used to uplift to new EBR Enabled Base Server Framework and Delivery Continuity - Technical Documentation For IFS Cloud

 

Regards


ashen_malaka_ranasinghe
Hero (Employee)
Forum|alt.badge.img+14

Hi ​@ZTC ZTC JGOTA,

The upgrade process from 24R2 to 26R1/26R2 is generally different from the traditional Apps 9 → Apps 10 style upgrades that many of us are familiar with.

For IFS Managed Cloud customers, the upgrade is normally performed in a separate non-production environment first, using a copy of the customer's data. The upgrade activities, technical validation, and customer testing are carried out on that upgraded environment before any production cutover is considered. Therefore, it is not typically a case of directly upgrading the live production environment. The production environment remains on the current release until the customer has completed testing and approved the move to the target version. This aligns with how IFS Cloud Lifecycle and Release Update processes maintain separate tracks for assessment, testing, and deployment.

Regarding the Lifecycle environment, IFS Cloud uses the Application Lifecycle Experience (ALE) and Release Update mechanisms. In practice, the upgrade work is usually performed through a separate release-update branch and upgraded environment rather than by immediately replacing the existing Lifecycle setup. The current customer environment continues to operate on the existing release while impact assessments, release update activities, and testing are performed on the upgraded version. Only after successful validation and customer acceptance is the upgraded solution promoted toward production.

For more information refer to: 26R1 - Impact Assessment and Release Update Assessment | IFS Community

For the testing timeline, the upgraded environment is typically made available after the initial technical upgrade and validation activities have been completed. This environment is then used for functional testing, regression testing, integration testing, reporting validation, and verification of customizations and configurations. The exact timing varies considerably depending on factors such as database size, number of integrations, level of customization, reporting landscape, data volume, and any remediation work required due to functional or technical changes between releases. Because of these variables, there is no universally applicable duration from project start to test-environment availability. The best source for an estimate is usually the IFS Upgrade Project Team or Cloud Operations team assigned to the specific engagement.

One best practice I would strongly recommend is to start reviewing the 26R1/26R2 Release Notes, Technical Documentation, Upgrade Considerations, and Deprecation Information as early as possible. Pay particular attention to customizations, integrations, reporting solutions, permission sets, and any technology changes introduced in 25R2 and later releases, especially areas related to Near-Zero Downtime (NZD), EBR compliance, and other platform-level enhancements that may require uplift activities before the final upgrade.