Question

Which posting control I am missing for project time reporting

  • 12 September 2022
  • 1 reply
  • 79 views

Userlevel 7
Badge +16
  • Hero (Customer)
  • 554 replies

Community, 

 

wondering which posting control I am missing for report project resource time. please refer to the screenshot. 

i have reported the hours against the project using correct report code, but there is no Reported Hours reported to the project. not sure which posting type i am missing to set up. 

Thank you.


1 reply

Userlevel 7
Badge +28

Look at PRJT1 and PRJT2 first.

 