What is purpose of partial project completion

  • 20 December 2021
  • 1 reply
  • 169 views

Userlevel 5
Badge +9
  • Sidekick (Partner)
  • 35 replies

 

Hi,

what is the purpose by using “partial project completion”?

For example , see below in green”, project completion at 70%.

The partial completion needs too a posting control “GP18”, what is the point too?

 

Thanks a lot

 

 

icon

Best answer by Thomas Peterson 20 December 2021, 17:01

View original

This topic has been closed for comments

1 reply

Userlevel 7
Badge +18

Hi, 

Partial project completion may be use for many different reasons.  

For example assume a project is used to create N fixed assets and these assets are placed in service periodically during the project.  

Another example could be that the client wants to recognize a portion of the revenue / cost leaving the project open for other activities. 

Another example could be that  a project is mostly completed, but it remains open for additional work such as final inspections, and warranty work. 

Partial completion can be done for many reason, the above are just a few that come up frequently.  

Best regards, 

Thomas