Hi All 

I have some posting controls setup for T1 and 2 that define Code parts A,B,C which seem fine however on the T1 postings for labour i am seeing Code part D being used as well which is correct but i have no posting control in place. 

Does anyone know if there is any rules or processes that would add this extra code part in ?

2 replies

Forum|alt.badge.img+7
  • Hero (Partner)
  • 29 replies
  • March 20, 2025

Hi Joshua,

I would recommend checking whether there is any Code String Completion or any GL Automatic Posting Rules which exist and could be triggering this.

Thanks,
Chris


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Customer)
  • 2 replies
  • March 20, 2025

Hi Chris

I don't have any setup. What i have noticed is that on the work order and work task the pre-posting is being populated at the point of creation with the correct stream, so i am wondering if there is something around how the pre-postings are being created