Planned Committed costs and Standard Planned Parts

  • February 23, 2026
  • 1 reply
  • 19 views

Good Afternoon,

I am looking for some guidance on project cost behaviour in an engineer-to-order environment.

We manage our builds in Project Navigator, with most demand originating from customer orders and driving inventory supply. Our BoMs are multi-level and complex, often containing thousands of components. It is common for standard planned items to be allocated to project-specific demand as part of the MRP process.

We have observed significant differences between:

• Planned Committed cost (post-MRP)
• Committed (released) cost
• Completed / Used cost

On investigation, it appears that standard planned components are not included in Planned Committed, only once  unless they are converted into a supply order (e.g. PO or released shop order) and connected or reserved to the project.

In our forecast process, ETC is currently set based on Planned Committed. This is leading to material under-forecasting, as large portions of standard planned demand are excluded. As a result, our Estimate to Complete can appear significantly understated in earlier phases of the project.

My assumption was that Planned Committed would reflect both:

• Project supply requests generated via MRP
• Standard planned cost associated with required BoM demand

However, it seems that this is not the case

Could anyone confirm whether this is the expected behaviour of Planned Committed cost in a project-manufacturing context with standard planned items?

Is there a configuration or alternative approach that allows the forecast to consider the full remaining requirement?

Would it be more appropriate to base ETC on Previous EAC or Previous ETC in an engineer-to-order model, however still need to understand planned committed as actuals can vary to the planned significantly.


I am particularly keen to understand clearly what is structurally included and excluded from Planned Committed, so we can determine whether our current forecasting logic is aligned with operational reality.
 

Many thanks in advance.

1 reply

Manxmano
Sidekick (Customer)
Forum|alt.badge.img+7
  • Sidekick (Customer)
  • March 10, 2026

Assuming you are doing cost roll-ups regularly to reflect BOM changes, if you have a project connection at the top level, the planned committed cost for the top-level shop order should include all material that's planned to be consumed to make that part (both std and PMRP planned). But once you start to make and buy parts, the way costs move from planned committed, to committed and then to used is sometimes not clear. They will move but as you have seen, std planned orders will go in through a direct used cost when they are consumed on a project connected order. But this can be quite late in the cycle giving you zero visibility and no control until it happens. Unless you go completely PMRP!