Hi,
I have a scenario where Project Pre Posting is not setting in the PICK IN and PICK OUT transactions.



Where can I set this up?
Thank you in advance.
Hi,
I have a scenario where Project Pre Posting is not setting in the PICK IN and PICK OUT transactions.
Where can I set this up?
Thank you in advance.
Hi
Thanks for raising this — based on your screenshots, the Project isn’t being populated during inventory transactions (PICK-IN / PICK-OUT) even though your Business Event configuration is set to “Include Project.”
Here’s what you can check to ensure it works end-to-end:
From your second screenshot, you’ve already enabled:
Project Pre-Posting: “Include Project” on both M1 and M3 posting types.
Great — this means the system can include project details if provided.
In your Posting Control setup for M1, I don’t see a Control Type for the “Project” (usually AC22 or similar) listed in the Code Part Columns.
You’ll need to:
➤ Add a Posting Control line for Code Part = “Project”
Control Type: Usually AC22 – Project Connection
Posting Type: M1 (Inventory), and also check M3 if applicable
Override: “Allowed” (optional, depending on config)
Without this, even if the Project is available in the transaction, the system doesn’t know how to post it — so it skips it.
If you're using pre-defined code string templates, make sure the “Project” dimension is enabled and mapped for Inventory/Project-related postings.
Once the Project is included in the Posting Control for M1 and/or M3:
Re-execute a test PICK-OUT or PICK-IN.
Check the Inventory Transaction History > Accounting tab.
You should now see the Project populated.
Make sure the Project ID exists and is active in the current company/site. Invalid or mismatched project setup can also silently block the pre-posting from completing.
Let me know if you'd like help setting up the control line or want a sample configuration.
Best regards,
Aaron J. | Solutions Architect
Hi
Thanks again for your question!
Here are a couple of IFS Cloud 24R2 documentation references that may help as you continue working through your setup:
Posting Types and Control Types
This section provides detailed information on setting up posting types and control types, including how to configure control types like 'AC22 – Project Connection' for specific code parts such as 'Project'.
Link: Posting Types and Control Types - Technical Documentation For IFS Cloud
Events in IFS Cloud
This section explains how events can be used to automate actions within IFS Cloud, including the configuration of business events that may impact inventory transactions.
Link: Events - Technical Documentation For IFS Cloud
Best regards,
Aaron J. | Solutions Architect
Hi
Thank you very much for your reply.
It seems I cannot use control type AC22 here.(I don’t have an option to define multiple projects in posting control details)
I can see project pre-posting for other MI postings like ARRIVAL. However, I cannot see it only in the PICK IN/PICK OUT transactions.
Thank you.
Hi
Thanks for the follow-up!
If you’re aiming to connect Projects to inventory transactions (like PICK-IN / PICK-OUT), you can try adding the AC22 – Project Connection control type to your Posting Controls for both M1
and M3
Posting Types. Here's what that looks like from a recent setup I did:
Posting Control Entry for M1 and M3:
Code Part Name: PROJECT (or Code Part C)
Control Type: AC22 – Project Connection
Valid From: A date before today (e.g., 2024-01-01)
Override: Not Required unless you want to allow exceptions
One thing to watch out for:
Changing the Pre-Posting setting from "No" to "Yes" typically requires IFS Developer Studio access. If you don’t have that, you’ll need to:
Submit a request to your IT/IFS Admin team, or
Work with your hosting partner if you’re on a managed environment.
Once you’ve configured the Posting Control, the Project won’t appear automatically unless it’s sourced from one of the following methods:
Method | When to Use |
---|---|
![]() | For real-world, planned material usage |
![]() | For sandbox/testing (if manual entries allowed) |
![]() | For service/maintenance scenarios |
I hope this helps!
Best,
Aaron | Solutions Architect
Hi
Thank you very much for the further help.
Do we need to set up any details for M1 and M2 posting controls you have mentioned above?
Thank you.
Hi
If everything is correctly configured for M1
and M3
, but the Project still isn’t appearing in the Inventory Transaction History, it’s worth checking whether the Project’s Posting Group has been assigned — this is a key dependency for project-related financial posting in IFS.
Every project should have a Default Posting Group. This determines which Posting Control rules IFS uses to generate GL entries for project-linked transactions.
If the Posting Group is missing:
The system may not know how to resolve the GL account.
It can skip the Project entirely or silently fail to post it.
If you don’t see the Posting Group field in the Project screen, it may be hidden or restricted based on your user role. You’ll need to work with your IFS Technical Team or System Admin to verify and assign the correct value.
1. Posting Control – Valid From
Make sure the Valid From
date on the PROJECT (Code Part C) line in Posting Control is before today’s date.
If it's set to today, the system may skip it depending on the transaction’s timestamp.
2. Pre-Posting Enabled on Business Events
Go to: Business Event > Posting Info
for PICK-IN and PICK-OUT
Ensure:
Pre-Posting = Yes
Project Pre-Posting = Include Project
If this field is locked, it may require Developer Studio access or a configuration update from your IFS admin.
3. Transaction Source Includes the Project
The project must be introduced from one of the upstream sources:
Source | What to Check |
---|---|
Project Demand Line | Material line includes the correct Project ID |
Manual Inventory Entry | Project is entered manually (if allowed) |
Work Task | Work Task is linked to the correct Project |
Customer Order Line | Project connection exists at line or header level |
4. Code String Includes Project
Navigate to: Accounting Rules > Define Code String
Confirm Project (Code Part C) is active
Ensure it’s not disabled or hidden for inventory transactions
Wishing you success!