Question

Not allowed to enter code parts when expense line is connected to a Work task

  • 3 May 2023
  • 2 replies
  • 33 views

Badge +2

While entering an expense sheet, we would like to manually edit the code parts attached to the expense line (This is attached to a work task). However we are not allowed to manually edit the code parts.

 

Is this an inbuilt control to prevent postings manually to a work task or is there a way we can manually modify the code parts?

 

 


2 replies

Userlevel 3
Badge +5

@NovAntonF - were you able to figure out the cause of this error? We are experiencing it too in IFS Cloud environments. I have never run into this issue with Project Activities that are connected to expenses. 

 

Thank you,

  Nik 

Badge +2

Unfortunately no.. We did not deep dive into it as this particular case was less important.

 

Kind Regards,

Antony

Reply