Hi,
I need help with a financial project with following setup
Capitalization posting method - Periodical
Project Type - Capitalize Rev/Exp
Revenue recognition method - POC Revenue First
POC Method - Actual cost
Revision Accounting - Catch up
Post Actual and recognized revenue difference - Checked
The project has some Actual Revenue and Zero Actual cost. When i run the Periodical Capitilization and Renevue Recognition, there is no revenue recognition voucher was created. May i know which set up is triggering to create no voucher
Best regards
Zuha