In a shop order, when there is a variance, I get detailed breakdowns of material, labor, machine and subcontracting costs in individual buckets and INVTRANHIST transaction.

However, when I manipulate something on a production schedule and capture a variance, I am JUST getting a single PSDIFF transaction and that is NOT broken out by material, labor, machine and subcontracting costs.

Has anyone encountered this and if so, how did you do a detailed variance analysis of production schedules to break out and report on material, labor, machine and subcontracting costs???

0 replies