Good Day;

in our project, STD-111A, Activity  100000412 is already released so we can’t use it in the manual supplier match process.

how we can extend the activity?

 

 

 

Hi @Nagah.khaled 

Good day!
Do you mean, you would like to extend the activity dates? If so you can perform it in ‘Activity’ window → Under General tab → There is a section for start/finish dates

 

Best regards

Zuha


thank you; i extended the activity and it solved the issue.

but this modification will affect the project it self or not.

 


Hi,

This change will only affect the Activity of that project and not the entire project