Good Day;

in our project, STD-111A, Activity  100000412 is already released so we can’t use it in the manual supplier match process.

how we can extend the activity?

 

 

 

Best answer by Zuha Samsudeen

Hi @Nagah.khaled 

Good day!
Do you mean, you would like to extend the activity dates? If so you can perform it in ‘Activity’ window → Under General tab → There is a section for start/finish dates

 

Best regards

Zuha

This topic has been closed for replies.

3 replies

Zuha Samsudeen
Hero (Partner)
Forum|alt.badge.img+10
  • Hero (Partner)
  • 61 replies
  • Answer
  • January 17, 2022

Hi @Nagah.khaled 

Good day!
Do you mean, you would like to extend the activity dates? If so you can perform it in ‘Activity’ window → Under General tab → There is a section for start/finish dates

 

Best regards

Zuha


Forum|alt.badge.img+14
  • Author
  • Hero
  • 110 replies
  • January 17, 2022

thank you; i extended the activity and it solved the issue.

but this modification will affect the project it self or not.

 


Zuha Samsudeen
Hero (Partner)
Forum|alt.badge.img+10
  • Hero (Partner)
  • 61 replies
  • January 17, 2022

Hi,

This change will only affect the Activity of that project and not the entire project