Skip to main content

Hello,

How to check in IFS the work in progress in the previous period

Current production in progress is easy to check, as there is such a report in IFS, but for the previous period there is not. 

 

We had our IT dept program a crystal report based on the GL voucher row table (GEN_LED_VOUCHER_ROW_UNION_QRY) so we could see the balance at month end or whatever date you use in the query.