Question

Does AFP Revenue Recognition Generate Corresponding Buyer-Side Expenses in Intercompany Transactions?

  • Nov 26, 2026 9:35 AM UTC
  • 1 reply
  • 8 views

In an intercompany project scenario, does IFS provide a standard process where:

  • an intercompany Sales Contract is mirrored as a Subcontract Contract in the receiving company;
  • revenue recognized through AFP in the selling company automatically generates the corresponding recognized cost in the buying company?

Or is the buyer-side recognition managed separately through project cost recognition and accounting rules?

Any feedback or implementation experience would be appreciated.

1 reply

richardwoods
Do Gooder (Partner)
Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 26, 2026 10:50 PM UTC

Short answer: I would not rely on the selling company's AFP revenue to drive the buyer's cost on its own. The two sides are normally set up and recognised in their own company, so plan the buyer side as its own piece of setup and test it with one small contract.

What the selling side does

  • Revenue through AFP follows the Invoice Method on the application. If the application is invoiced on submit, the project invoice carries the revenue postings and no separate AFP postings are made.
  • If transactions are to be invoiced through AFP, the report codes used for cost and time should be set to Not Invoiceable. Otherwise they can also be invoiced separately.

What to set up on the buyer side

  • The cost recognition in the buying company is driven by that company's own project and subcontract setup, so start there: the Sub Contract connected to the buyer's project, and the project accounting rules on the buyer's project.
  • If you want accruals for the subcontract cost, the subcontract must be connected to the project, the project must be in Approved, Started or Completed status, and the basis for the sub contract accrual calculation must be defined. They are then created in the Periodical Capitalization and Revenue Recognition run.
  • If the two companies are meant to report cost across each other, the multi-company project reporting setup (the Activity Link Setup) and its posting types, with due to and due from affiliated company, are worth comparing with what you need.

Things to know

  • I would not assume the receiving company's subcontract is created for you from the sales contract. Confirm that on a small test contract before building the process around it.
  • Test the buyer side with the same invoice method you will use in live, since that changes which postings exist on the selling side.

Worth a look: the IFS Cloud documentation for Application for Payment, Submit Application, Multi-Company Project Reporting Setup and Periodical Capitalization and Revenue Recognition.

Which companies and project types are involved, and is the buyer's cost meant to be recognised from the sub contract valuation or through multi-company cost reporting?