Hi Experts.
When I created a Request, I notice that some Tasks are transferred to PSO with the status "DO NOT Schedule" immediately after creation. However, this does not happen for all Tasks—only for some of them.

I have also verified that the "Manually Schedule" flag is not set to TRUE for these Tasks.

I still can see these tasks in PSO as Do not Schedule.


As I noted this only happens for tasks having Dependncies only.
Question is how we can setup is so all NEW tasks appear in PSO in as "DO NOT Schedule" activities? I cannot find the exact toggle or an option that it will do the as above for all Tasks but not just for few?
Thanks
KM