Hi Team,

In PSO > Scheduling > Resources, when dispatcher wants to assign a task, he needs to be able to see the teams and not only the resources.  As per our business requirements, Task has to assigned to the team itself. This team belongs to the same dataset where we are trying to assign task manually. 

We also tried assigning division to the team, but it didn't work. 

We understand Teams are like resources and should be visible. 

 

Regards,

Shalu

 

Is your problem that you don’t see the Team itself as a row in the Gantt chart? If yes, did you create shifts for the team?