Our customer has following scenario:

Some technicians have different regular duties (e.g. office work) during their normal day, and they should be seen as absent in PSO. In this case, the easiest way to build this in the system would be to create miscellaneous resource allocations as recurring. 

For example, technician X is absent each Monday morning from 8 to 12.

Does anyone know if this will be available in the near future?

Thank you very much.

 

Best regards,

Iulia

 

You asked, we delivered… 😁

 

Recurring MRA - Misc. Resource Allocations (25R1­)

Recurring MRAs can be established over a customizable timeframe and aligned with a resource's shift pattern. For example, a shift planner may need to schedule an MRA for a team meeting every Friday at 9:00, or a recurring 30-minute MRA for each technician at the beginning of their shift. This can be efficiently managed through a single recurring MRA parent record, eliminating the need to create individual MRAs for each instance.

 

 


One method is to create a Recurring MRA at Resource Management>Resource Allocations> Recurring Miscellaneous Resource Allocation, and then add the resources.

The second approach is to use the Assistant at Resource Management>Resource Allocations>New Miscellaneous Resource Allocations. This allows you to filter resources by various criteria and create the MRA:

Recurrence Start/End and Interval define the period, during which MRAs will be generated. The individual MRA allocations can be reviewed on the Schedule tab, they will also be sent to PSO immediately.

 

Unfortunately the Demystified update for 25R1 is delayed this time...


Such a great timing, such good news. Thank you, ​@Alexander Heinze!


Reply