Question

PSO Parameter - SelectableCommittedActStatuses

  • 12 December 2022
  • 1 reply
  • 41 views

Userlevel 1
Badge +2

Hi,

 

In the PSO parameters menu we modify the parameter "SelectableCommittedActStatuses" with the values "Do Not Schedule" and "Accepted".
But when we have a task in the "Commited" state, when we analyze which are the possible states to update, other states are showing up than the ones we assigned to the parameter, it seems that it's not filtering:

 

 

 

Are we having a misinterpretation of what this parameter is supposed to do?

 

Best regards

 


1 reply

Userlevel 4
Badge +11

Hi João,

Would you like to raise an issue so we can investigate further.

Thanks,

Kai

Reply