Could someone please help me with this issue. I have created a obstructive maintenance work which can be clearly seen in the both visual shop order operation planning as well as smart manufacturing planning board. This obstructive work is overloading the work center on which the operations are already planned. So, now as per MSO functionality, the operations need to reschedule for the other days where work center is available but this is not happening after finite scheduling and operations are getting loaded on the days of maintenance work.

Also attached the MSO load file for further reference.

 

 

 

Regards,

Mithun K V

Hi All,

I haven't mention the planned duration in the work task, instead I had only entered planned start date and finish date. After entering the duration on the work task, the obstructive works are considered in MSO.

Regards,

Mithun K V