Hi Experts,
We have a requirement to add new fields in the Activity Tooltip like Post code and Region of the Work Task. Could you please guide how to achieve that. Attaching the doc for your reference.
Regards,
RR
Hi Experts,
We have a requirement to add new fields in the Activity Tooltip like Post code and Region of the Work Task. Could you please guide how to achieve that. Attaching the doc for your reference.
Regards,
RR
This is bit critical.
Check this document on page 40. In PSO, change the list mentioned here:
These are the lists you are likely interested in:
Just recognized that you wanted city and post code, these exist already, so just add them to the list:
This doesn’t work for region though, as task to region is 1:n, so you may want to consider using an additional attribute as explained in the document.
Thanks for your response . Will check and get back to you if any issue.
Regards,
RR