Can a manual commitment over ride the prerequisite demand of a job ?

FSM has sent the prereq over OK:

7275 should be scheduled before 7274, but PSO has scheduled them the other way round, I notice in FSM that these have been committed by a user rather than the system. Would this over ride the prereq set on the job ? Task 7274’s SLA doesn’t start until the day after, so the system would not have been able to schedule it. (plus it’s out of shift when committed).

 

Thanks for any help

Hi Keith,

Yes.  The activity group only applies to schedulable activities, once they are committed then the committed activity ordering rules apply - the activity which is committed first will be placed first in the route.

Thanks,

Tom