Skip to main content
Solved

PM Action Work order generation

  • January 9, 2024
  • 2 replies
  • 220 views

Forum|alt.badge.img+3

Hi All,

 

I have PM actions set up in one of our test environments. What a work order is generated from the PM action the work order and work tasks are at status of released. 

 

However when I have duplicated this in another environment the work order and work tasks stay at status New. 

 

can any advise if there is a parameter that i need to update to get them to go straight to status released 

 

We are using IFS Cloud 23 R1

Best answer by ajnsse

You will have to configure the Object Property: PM_DEF_TASK_STATUS and set that to the status of RELEASED.

2 replies

Forum|alt.badge.img+8
  • Hero (Employee)
  • Answer
  • January 9, 2024

You will have to configure the Object Property: PM_DEF_TASK_STATUS and set that to the status of RELEASED.


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Customer)
  • January 9, 2024

Thank you