Why is MSO not scheduling the operation even though I have available capacity?

As you can see in Picture 2, there is available capacity, but no operation has been planned. The operation status is unscheduled (Picture 1).

Initially, scheduling worked as expected, and the operations were assigned. However, for testing purposes, I reduced the lot size from 500 to 300 pcs, which also led to a corresponding reduction in lead time.

For some reason, the operations were removed from the resource, and the status of the operation changed back to unscheduled, as shown in the picture.

I do not see a connection here.

Add: We do use MSO module and is connected to PSO. 
 


 

 

Forum|alt.badge.img+5
  • Do Gooder (Partner)
  • March 27, 2025

Hi,

There are numerous reasons they can be left unscheduled and unfortunately I don’t think MSO shows anywhere the reason. I recently found for example that many orders were unscheduled as the calendar I had attached to the labour class was in a changes pending state, so even though I had labour capacity calculated, the MSO could not use it.

It seems checking basic data is a task that needs performing, but I would start by checking your calendars