When using multiple Servers in a farm, how would we know which server would process the schedule process? How does FSM make sure that no 2 servers are running these processes at the same time?
When using multiple Servers in a farm, how would we know which server would process the schedule process? How does FSM make sure that no 2 servers are running these processes at the same time?
Hi Martand,
any of the available Application Servers can pick up the schedulded process. You can’t determine/influence which Server will execute it.
The alternative is to move the scheduled process to a Integration Monitor schedule instead, which allows you to specify the Application Server which it will run on. That way you can distribute the load for schedules accross multiple machines.
Best regards
Roman