Hi Team,

Is there any option available in PSO to easily identify 2 man task in PSO - Resources screen. I can see we have link task which shows in PSO - Task screen.

In our previous used tool if i click 1st task it will automatically shows link to another task in engineer Gantt.

In below example we have assigned 2 man task for 2 FT, but as planner we cant easily identify it.

 

we need some identity like below in Resources screen.

Regards,

Shiyaz

 

 


3 replies

Userlevel 4
Badge +13

Hi Shiyaz,

 

The only indicator is on the Activity fly-out panel. The legend does not identify an indicator for linked activities.

 

 

Userlevel 3
Badge +8

Hi,

 

Can i add the linked task details in tooltip? If so can you please let me know how to add?

 

 

Regards,

Shiyaz

Userlevel 4
Badge +13

Those attributes are not available in the Lists to configure the tooltip. Section 7 of the Administration guide lists the valid fields and Linked Activities are not listed there.