Hi Team,

Is there any option available in PSO to easily identify 2 man task in PSO - Resources screen. I can see we have link task which shows in PSO - Task screen.

In our previous used tool if i click 1st task it will automatically shows link to another task in engineer Gantt.

In below example we have assigned 2 man task for 2 FT, but as planner we cant easily identify it.

 

we need some identity like below in Resources screen.

Regards,

Shiyaz

 

 

Hi Shiyaz,

 

The only indicator is on the Activity fly-out panel. The legend does not identify an indicator for linked activities.

 

 


Hi,

 

Can i add the linked task details in tooltip? If so can you please let me know how to add?

 

 

Regards,

Shiyaz


Those attributes are not available in the Lists to configure the tooltip. Section 7 of the Administration guide lists the valid fields and Linked Activities are not listed there.