Skip to main content
Question

identifying 2 man task in PSO

  • December 12, 2022
  • 3 replies
  • 40 views

Forum|alt.badge.img+8

Hi Team,

Is there any option available in PSO to easily identify 2 man task in PSO - Resources screen. I can see we have link task which shows in PSO - Task screen.

In our previous used tool if i click 1st task it will automatically shows link to another task in engineer Gantt.

In below example we have assigned 2 man task for 2 FT, but as planner we cant easily identify it.

 

we need some identity like below in Resources screen.

Regards,

Shiyaz

 

 

3 replies

ishD
Hero (Partner)
Forum|alt.badge.img+13
  • Hero (Partner)
  • December 12, 2022

Hi Shiyaz,

 

The only indicator is on the Activity fly-out panel. The legend does not identify an indicator for linked activities.

 

 


Forum|alt.badge.img+8
  • Author
  • Sidekick (Customer)
  • December 13, 2022

Hi,

 

Can i add the linked task details in tooltip? If so can you please let me know how to add?

 

 

Regards,

Shiyaz


ishD
Hero (Partner)
Forum|alt.badge.img+13
  • Hero (Partner)
  • December 13, 2022

Those attributes are not available in the Lists to configure the tooltip. Section 7 of the Administration guide lists the valid fields and Linked Activities are not listed there.