Skip to main content
Question

FSM Schedule Process

  • October 10, 2024
  • 2 replies
  • 41 views

Forum|alt.badge.img+5

Hi,

We have a requirement to send the change data of skill availability from FSM to PSO through Schedule Process, and it should not send the data through LOAD operation. Is it possible to implement the change through schedule process.

 

 

2 replies

SAMLK
Hero (Partner)
Forum|alt.badge.img+14
  • Hero (Partner)
  • October 22, 2024

Hi @preethi.a05 

FSM does not have a built-in mechanism (out of the box) to send only skill availabilities without initializing the load using the perform_initialize_threesixty MPM as far as I can recall.


Forum|alt.badge.img+5
  • Author
  • Sidekick (Partner)
  • October 24, 2024

 Hi @SAMLK ,

 

Initialization is fine, LOAD will happen everyday on a specified time but it should not send resource skill availability data in that, it should only send if a CHANGE happens.