Question

Earliest Start - Request Work Task

  • Jan 17, 2024 1:22 PM UTC
  • 2 replies
  • 33 views

Forum|alt.badge.img+7

Hello,

I was testing the new release and I have seen this new field Earliest Start. Does anyone know when or if it is triggered by something in particular? I know I can add a time and date manually, but I was wondering if it’s also filled in automatically.

 

 

Thank you very much,

Iulia

2 replies

Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+25

It’s not a new field, it did exist in previous releases and also in Work Order Management. See if this helps:

 


Forum|alt.badge.img+7
  • Author
  • Sidekick (Partner)
  • Jan 18, 2024 2:14 PM UTC

Hi @Alexander Heinze, thanks for the explanation. This definitely helps.