Hi - I’m using Dispatch Console doing a manual Allocation process in 25R1. 

 

I’d like the View Eligible Resources button to filter my Resources by Region availability AND the Valid From - Valid To Dates. See my example below, this Resource will be available in the CENTRAL Region throughout August 2025 - Work Task Object’s Region is CENTRAL.

 

In practice, I have a Request Work Task with a Planned Start of today’s Date, when I select Request Work Task, the View Eligible Resource button does not remove this Resource from the list as it should (as this Resource is not scheduled until August 2025) - but the Planned Start Date is today - therefore they should be in-eligible and filtered from the list.  

 

The View Eligible Resource button seems to ignore the Valid To and Valid From Dates on the Scheduling Resource Regions. Am I missing some other date parameter on my Work Task that the button checks? Or does it ignore the dates completely on the Schedule Resource Regions? 

 

Many thanks in advance!

Tom

 

FYI here’s Alex H’s Scheduling Demystified document re. this View Eligible Resources:

 

I don’t think availabilities are considered nor is there a way to include this in your search. Haven’t tried it but I’m pretty sure it’s the same for other constraints with availabilities (e.g., skills). Might be worth logging an idea.