Hi there IFS community!


We want to manage both internal cost and potential sales price based on Time Type — without splitting the resource group?

 

For example, electricians working during daytime cost the business $100/hour, but if they work at night, they cost $180/hour — all within the same resource group, but using different report code or Time Type?

 

Is it possible to configure this in IFS Cloud without needing separate inventory parts or resource groups — just by using Time Type  and internal price configuration?

 

 

Thanks in advance!

 

 

4 replies

Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • Jun 18, 2025 12:38 PM UTC

This is for registrating work task hours within a resource group through work orders and work tasks in the maintenance or service module in IFS.


kasunhp
Hero (Partner)
Forum|alt.badge.img+10
  • Aug 27, 2025 1:28 PM UTC

​@endreavinor 

Hi,

Did you solve this issue?

I also have this kind of requirement?

 


Forum|alt.badge.img+5
  • Do Gooder (Partner)
  • Feb 18, 2026 6:55 PM UTC

Yeah I am looking for this answer as well. Looks like there is no way other than different resource groups


kasunhp
Hero (Partner)
Forum|alt.badge.img+10
  • Feb 18, 2026 8:39 PM UTC

Yeah I am looking for this answer as well. Looks like there is no way other than different resource groups

Time types will fetch different sales parts only. It seems we need different resource groups for different standard costs.