Question

Data transfer from IFS Cloud to PSO

  • Nov 2, 2026 5:19 PM UTC
  • 4 replies
  • 25 views

Forum|alt.badge.img

We have integration between IFS Cloud and PSO, For the dataset in Scheduling dataset Parameters scheduling work days is set to 5 and Appointment window is set to 30 Days

 

We are using Appointment as the process type of our schedule, However i can see order with SLA start of March 2027 also visible in PSO,Is this valid since i would expect orders whose SLA start is within the next 35 days to be visible in PSO.

 

 

 

4 replies

Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+25

What’s the end of the SLA? If it falls within the optimization horizon, PSO can still schedule it.


Forum|alt.badge.img
  • Author
  • Do Gooder (Partner)
  • Nov 3, 2026 8:34 AM UTC

What’s the end of the SLA? If it falls within the optimization horizon, PSO can still schedule it.

The SLA end date is also after March.

However the issue is not that the orders are not scheduled. My main concerns is that i don’t want this order to be visible in PSO and as it falls outside teh 35 day window my understanding is it should not be transfeered

 

Am i missing anything


Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+25

Yes, but when exactly does the SLA end? If - for example - it ends tomorrow (or anytime in the next 35 days) then it would make perfect sense to send it to PSO and schedule it.


Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+25

If have checked with R&D and got the following answer:

The first checks are the dataset’s minimum status (Schedule from Task Status and Schedule from Request Task Status, default Released) and the dataset link. Work order tasks follow the maintenance organization site, and Request tasks follow the service delivery unit or, if that has no dataset, the service organization. A task also has to fulfill the below requirements as well:

  • Not be excluded from scheduling
  • Not Finished or Cancelled
  • Has a person or crew resource demand

On top of that, the calculated scheduling period has to overlap the scheduling window (Scheduling Work Days + Appointment Work Days). That period is the primary and secondary SLA periods, pulled back one day at the start, not only the customer SLA. This is the same for both work tasks and request tasks.

Can you check primary and secondary SLA periods on the tasks that you would NOT expect to see in PSO? Maybe share screenshots.