committed activities are uncommitting after a second in pso

  • Aug 4, 2025 6:34 AM UTC
  • 3 replies
  • 93 views

Forum|alt.badge.img+7

Hi All

committing activity through schedule information tab when I change the status of an activity in PSO from Allocated to Committed, the change is being made, but after a few seconds the status changes automatically to Allocated again.

Has anyone encountered something like this?

 

 

 

 

 

 

 

Best answer by Sajith Anushan

Okay, check whether committed tasks are setting to schedulable once again from FSM side, or workbench update is not properly processed in FSM side. 

View original

3 replies

Forum|alt.badge.img+22
  • Superhero (Employee)
  • Aug 15, 2025 5:36 AM UTC

Is this FSM-PSO integrated environment?


Forum|alt.badge.img+7
  • Author
  • Sidekick (Partner)
  • Aug 18, 2025 6:22 AM UTC

Hi Sajith,

 

Yes 


Forum|alt.badge.img+22
  • Superhero (Employee)
  • Answer
  • Aug 18, 2025 10:57 AM UTC

Okay, check whether committed tasks are setting to schedulable once again from FSM side, or workbench update is not properly processed in FSM side.