Skip to main content

Hi all,

We are having some issues regarding PSO activities AutoDuration.

We have defined the following PSO parameter:

           AutoDurationEnabledByDefault = FALSE

 

In the PSO menu "Activity Types", we have defined the tab Auto Duration Enabled as FALSE for all activity types.

 

 

 

Despite having these parameters configured correctly, PSO is still adjusting the activities' durations, making them shorter or longer.

Is there a parameter we might have missed? If not, can anyone help us understand why the durations are still being altered?

 

Thank you, everyone.

Hi - This parameter only governs activity duration adjustment based on Archive data. If you are using Skill Proficiencies or Override Durations, duration will be still adjusted.


Reply