Skip to main content
Question

Document Revision - Letter date works different than custom made date field

  • June 24, 2026
  • 1 reply
  • 16 views

Forum|alt.badge.img+1

In Doucument Revision we have added a custom field for ‘Contract Date’. This date field works a little different than standard field ‘Letter Date’ - the date has to be set, which requiers an additional click:

Any ideas on how to avoid this extra ‘Set’, so the field works the same way as ‘Letter Date’:

 

1 reply

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • June 24, 2026

Hi ​@HAFJASO,

Yes, it is possible. 

Please refer to the screenshots below.

  1. Configure Custom Field with Date Format Date & Time.
  1. Enable Showonlydate option for the custom field in page designer.

 

Regards

Abdul Rehman