We have created the purchase order from Work order purchase requisition and the work order is in related status and Purchase order in Planned state,  i am trying to cancel the purchase order , system is giving error “ there are peggings connected to purchase order lines, Remove the pegging first and then cancel the purchase order. How do i cancel the old purchase orders.


This topic has been closed for comments

5 replies

Userlevel 5
Badge +8

Hi Arif,

Can you please RMB on PO line, select “Unpeg” and try to cancel the PO then?

 

 

Userlevel 5
Badge +12

Hi,

You can unpeg inventory material purchase from the material line on the work task (rmb ‘Manual Pegging’).

Userlevel 5
Badge +10

Thanks @Thommy  but those items are of type Manufacturing.

Userlevel 5
Badge +10

@Thommy , i can see only manual pegging instead of unpeg for the items that are in received state.

Userlevel 5
Badge +12

You can just unpeg before the reciept. After recieving the material it will move from being pegged to being reserved.