Method to change structure status Plannable to Tentative

  • July 30, 2025
  • 3 replies
  • 51 views

Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • 22 replies

What method should I use to change the status Plannable to Tentative?

 


Thanks in advance,

Best answer by matt.watters

@Thean first you must Cancel the alternate (Status > Cancel) then you can set it to Tentative by the command Status > Review.

 

3 replies

matt.watters
Ultimate Hero (Partner)
Forum|alt.badge.img+26
  • Ultimate Hero (Partner)
  • 699 replies
  • Answer
  • July 30, 2025

@Thean first you must Cancel the alternate (Status > Cancel) then you can set it to Tentative by the command Status > Review.

 


Forum|alt.badge.img+6
  • Author
  • Do Gooder (Partner)
  • 22 replies
  • October 13, 2025

Hi ​@matt.watters ,

I Want to migrate the Unit costs value in Inventory Part. Could you pls help me out to identify which procedure to be used?
 

Thanks in advance,

Thean Mozhi
 


matt.watters
Ultimate Hero (Partner)
Forum|alt.badge.img+26
  • Ultimate Hero (Partner)
  • 699 replies
  • October 13, 2025

@Thean I do not know which procedure to use for this. Maybe that topic should be a new thread.