Hi,

In Aurena, where do I go to set/increase the batch queue processing power? i.e. number of migration jobs that can be run concurrently?

 

Thanks


1 reply

Userlevel 6
Badge +16

Hi,

If you go to batch queue configurations you can increase the number of processes to allow multiple jobs to be run at the same time as per below….

 

Regards,

Antony