Does the Supply Chain Part Groups work for Distribution Orders?

We are using Distribution Orders for Site to Site supply from a Manufacturing Site to Sales Sites.  We want to ship everything Sea except for Electronic Parts.

  1. I have the Supply Chain Matrix for Site set up, and have added an Exception for Electronic Parts.

     

  2. I added a Supply Chain Part Group to IFS Called “Electronic Parts”.

     

  3. I added the Supply Chain Part Group to the Inventory Part.

     

The system is still creating DOs with SEA for the part.

 

 

 


3 replies

Userlevel 5
Badge +13

Hi Jenifer,

Your configuration seems to be ok. I tried and the DO created manually is correctly fetching the parameters in my exception.

How do you usually create the Distribution Orders?

Regards,

Pilar

Userlevel 2
Badge +5

Hi Pilar,

We normally create them using Master Schedule (MS Level 1 and MS Level 2).

 

Thank you,

Jenifer

Userlevel 5
Badge +13

Hi Jenifer,

Sorry, but I’m not familiar with MS functionality, so not sure how to replicate the DO creation flow.

Then, I suggest you to open a Support ticket so this can be investigated with your configuration and actual data.

Sorry for not bein able to help

Regards,

Pilar