Supplier Schedule PO Line creation error

  • March 20, 2026
  • 1 reply
  • 14 views

Jeremy Soos
Do Gooder (Partner)
Forum|alt.badge.img

Hello Guys

 

Customer currently faces a problem that after MRP run, new supplier schedule with additional Lines will be created and connected to the PO but no further Line No / Release No will be created on the Purchase Order.

 


Did someone face the same problem or know what could be the solution?

Could it be because of the Cumulative Quantity?
 

 

1 reply

Jeremy Soos
Do Gooder (Partner)
Forum|alt.badge.img
  • Author
  • Do Gooder (Partner)
  • March 20, 2026

Ok so for everyone which has the same Problem:

Solution:
Supplier Agreement, make sure there is an active Supplier Agreement for this Part, if the Supplier Agreement is closed or just the Part line status is closed, Supplier Schedule will create no further Line No. on connected Purchase Order