Skip to main content
Question

Splitting The Line When PR is Generated from Project

  • March 5, 2026
  • 0 replies
  • 4 views

HoiJewelP
Sidekick (Partner)
Forum|alt.badge.img+9

Hello Community,

When the Purchase Requisition is created from Project Demand, customer is expecting to split the line and create multiple PO for that demand to cost saving. But As the PO is created from the Project system doesn’t allow to change it directly in the PR. And he procurement team doesn’t want to go to project team every time and ask to change the demand . Is there any way to solve the issue?