Shop Order Shortages (Future)

  • September 10, 2025
  • 1 reply
  • 42 views

Forum|alt.badge.img+3

I am working on a shortage report for shop orders material. I have a concept of if full required hasn’t been issued of that material by the date required and date required < today then its fine I can mark it as a shortage, I want to look for future shortages (90 days) and I am thinking how to do that? any ideas? how can I suspect if the future date required (Say 5 days from now) the part will be on shortage or not?

The only thought I have his to check if the SO/PO is against that demand (but that too is confusing how to do..)

Best answer by Abdul

Hi ​@marslan,

Simulate Multilevel Material Availability screen allows business users to simulate the raw material requirement against future demand/forecast. 

Simulation provides the required supply information, considering all your open supply, existing stock, and safety stock requirements.

Please refer to the screenshot below.

 

Regards

Abdul Rehman

1 reply

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • Answer
  • September 11, 2025

Hi ​@marslan,

Simulate Multilevel Material Availability screen allows business users to simulate the raw material requirement against future demand/forecast. 

Simulation provides the required supply information, considering all your open supply, existing stock, and safety stock requirements.

Please refer to the screenshot below.

 

Regards

Abdul Rehman