Safety Stock but split required for 2 warehouse in same site

  • May 27, 2025
  • 1 reply
  • 35 views

Forum|alt.badge.img+2

I am seeking possibilities in splitting the QTY into 2 warehouse within the same site

 

Site ABC

Warehouse 1

Warehouse 2

Safety stock for a part is 10, hence when we run MRP the supply is created for 10 but that need be distributed 5 to warehouse 1 and 5 to warehouse 2. Is there any possibility in achieving this.

1 reply

Marcel.Ausan
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • May 27, 2025

@feleciano so, MRP (planning parameters) are set at Site level.

Then once the stock is replenished (via PO for example) you can define Putaway Zones for this part and run the Refill Putawat Zones. This would create transport tasks to relocate the qty in the desired warehouses (5 pcs in WH1 and 5 pcs in WH2)