Solved

Route Canceled

  • 25 March 2024
  • 5 replies
  • 31 views

Badge +5

Hi,

I want to make the route unusable, but "update to obsolete is not allowed for the default alternate unless it has been phased out." returns error message. 

 

icon

Best answer by Richard Owen 25 March 2024, 09:36

View original

5 replies

Userlevel 5
Badge +12

Hi,

Try entering a Phase Out Date in this field

I hope this helps.

Badge +5

 

Hi Richard,

What processes will ending the material's validity date affect? We just want to cancel the route of the material.

Userlevel 5
Badge +12

My apologies, I was multitasking when I replied!

You should of course add the ROUTING Phase Out Date here

I hope this helps.

Badge +5

I tried but the same error comes up again.

Userlevel 5
Badge +12

Make sure the Phase Out Date is a date in the past (e.g., NOT today) 🙂

Reply